基于关键链的地下矿采掘计划编制优化方法

谭正华1,2(),文阳1(),王李管2,李国泰1   

  1. 1.湘潭大学计算机学院·网络空间安全学院,湖南 湘潭 411105
    2.中南大学数字矿山研究中心,湖南 长沙 410083
  • 收稿日期:2020-11-15 修回日期:2021-04-26 出版日期:2021-08-31 发布日期:2021-10-08
  • 通讯作者: 文阳 E-mail:33539318@qq.com;2749951540@qq.com
  • 作者简介:谭正华(1981-),男,湖南邵阳人,讲师,从事计算机图形学和数字矿山研究工作。33539318@qq.com

Optimization Method for Preparation of Underground Mining Plan Based on Critical Chain

Zhenghua TAN1,2(),Yang WEN1(),Liguan WANG2,Guotai LI1   

  1. 1.School of Computer Science & School of Cyberspace Security,Xiangtan University,Xiangtan 411105,Hunan,China
    2.Research Center of Digital Mine,Central South University,Changsha 410083,Hunan,China
  • Received:2020-11-15 Revised:2021-04-26 Online:2021-08-31 Published:2021-10-08
  • Contact: Yang WEN E-mail:33539318@qq.com;2749951540@qq.com

摘要:

为了解决传统地下矿采掘计划编制中存在的最短工期不可控、作业成本较高的问题,以最大化减少工期为目标,提出了一种资源约束下的采掘计划关键路径自动搜索方法。首先,根据作业之间的逻辑衔接关系自动生成采掘计划网络图,并为其添加资源约束;然后,根据工序顺序表和计划衔接表中的信息确定每个采场执行的工序,且不同工序按照不同的资源配置规则来分配优先级;最后,更新网络图,以当前作业为初始节点,采用改进的深度优先搜索算法遍历有向图,递归查找全部采掘路径,其中耗时最长的路径为关键路径,即资源约束下的最短工期。研究结果表明:运用资源约束下的关键路径自动搜索方法来实现采掘计划优化,缩短了计划编制的时间和采掘计划的工期,降低了作业成本。以乌拉特后旗紫金矿业三贵口矿山采掘计划编制为例,证明该方法能够有效优化矿山采掘计划。

关键词: 地下矿, 采掘计划编制, 关键链, 资源优化配置, 深度优先搜索算法, 网络图

Abstract:

Underground metal mineral have the characteristics that resources condition and underground conditions are complex,with diverse mining methods.Apart from this,mine production is always in an uncertain and constantly changing dynamic process.How to obtain a scientific and effective production plan quickly has always been an urgent problem for mining enterprises.In order to solve this problem,a variety of production planning methods are used in the production process of mines,such as multi-objective programming algorithm,mixed integer programming,genetic algorithm,quantum particle swarm optimization,critical path method,and so on.The risk of uncertain in production process of mines often result in fail to complete the project on time,which will have a significant influence on the reputation and income of the mining enterprises. For the purpose of solving the problem of uncontrollable shortest construction period and high operating cost existing in traditional underground mining plan preparation,an automatic search method for the critical path of mining plan under resource constraint was proposed.Firstly,a network diagram was generated automatically according to logical relationships (subsequent operations,start time,end time and process ID) between operations,and resource constraints for the chart need to be add.Then,the current process of each stope was determined according to the information in the process sequence and the plan connection table,and assigned priority to different processes according to different resource allocation priority rules.The priority of first process in every stope was assigned according to the earliest start time of the operation and resource demand intensity,and the priority of the remaining processes was determined according to the completion time of the previous process in process sequence and resource intensity.At last,the network diagram under resource constraint needs to be updated,taking current node as an initial node,an improved depth-first search algorithm was used to traverse the directed graph,and find all mining paths in current process recursively. The path that taken the longest time was critical path,which represented the current shortest completion time of the mining plan under resource constraint.The idea of critical chain was applied to the Sanguikou mine of Zijin Mining,and the result shows that the method uses for optimizing the mining plan makes full use of the advantage of critical chain management.The method not only solves the problem of resource constraint and the shortest construction period,but also shorten the time for planning and the time for mining plan.What is more,it reduces the operation cost.During the construction period,the adjustment and optimization of the mine plan were completed,and the sustainable and efficient production of the mine was realized finally.

Key words: underground mine, preparation of mining plan, critical chain, optimal allocation of resources, depth-first search algorithm, network diagram

中图分类号: 

  • TD853

图1

基于关键链的采掘计划编制流程图"

图2

网络图"

图3

资源冲突调度示意图"

图4

查找关键路径流程图"

表1

三贵口矿山530中段采掘计划衔接表"

行号采场序号采场编号工序序号开始时间结束时间所需资源后继采场序号
057530-5203(9-3,9)KC12020/4/82020/4/14358、59
22020/4/152020/4/183
158530-5202(9-3,9)KC12020/4/152020/4/21360
22020/4/222020/4/272
259530-5204(9-3,9)KC12020/4/152020/4/212Null
22020/4/222020/4/272
360530-5201(9-3,9)KC12020/4/222020/4/28461
22020/4/292020/5/23
461530-5204(9)KC12020/4/222020/4/27362
22020/4/282020/5/32
562530-5206(9)KC12020/4/282020/5/3265
22020/5/42020/5/72
663530-5207(9)KC12020/4/82020/4/13164
22020/4/142020/4/193
764530-5208(9)KC12020/4/142020/4/19265
22020/4/202020/4/252
865530-5209(9)KC12020/5/42020/5/9266
22020/5/102020/5/203
966530-5210(9)KC12020/5/102020/5/15467
22020/5/162020/5/224
1067530-5802(9-3,9)KC12020/5/162020/5/204Null
22020/5/212020/5/292
1168530-5803(9-3,9)KC12020/4/82020/4/19269
22020/4/202020/4/262
1269530-5803(9-3,9)KC12020/4/202020/5/3270、71
22020/5/42020/5/94
1370530-5804(9-3,9)KC12020/5/42020/5/12272
22020/5/132020/5/222
1471530-5805(9-3,9)KC12020/5/42020/5/113Null
22020/5/122020/5/173
1572530-6001(9)KC12020/5/232020/5/27373
22020/5/282020/6/32
1673530-6002(9)KC12020/5/292020/6/52Null
22020/6/62020/6/101

图5

三贵口矿山530中段采掘计划甘特图"

表2

采掘计划编制方案对比分析"

指标遗传算法关键路径法关键链
工期优化1.2%01.67%
成本--1%
有解非劣解有解最优解
解决资源冲突
时间复杂度ON*M*MaxgenOX*YOX*Y

图6

矿山采掘计划编制效果图"

Du Wenwen,Yang Yang,2020.Research on route search based on improved Dijkstra algorithm[J].Railway Computer Application,29(9):62-67.
Goldratt E M.Critical Chain[M].Beijing:Publishing House of Electronics Industry,2009.
Gu Qinghua,Yanhong Lü,Lu Caiwu,al et,2020.Modeling and algorithm of multi-objective production scheduling optimization for multi-metal open-pit mine[J].Metal Mine,49(4):147-153.
Gu Qinghua,Ma Long,Lu Caiwu,al et,2020.Long-term mining production scheduling model and optimization algorithm for open-pit mine enterprises[J].Industrial Engineering and Management,25(1):38-52.
Gu Xiaowei,Xu Xiaochuan,Wang Qing,al et,2014.Improving optimization algorithm of production scheduling for open-pit metal mine[J].Journal of Northeastern University(Natural Science),35(10):1492-1496.
Hou Jie,Hu Nailian,Li Guoqing,al et,2016.Dynamic optimization of production plans for multi-metal underground mines[J].Chinese Journal of Engineering,38(4):453-460.
Huang Junxin,Guo Xiaoxian,Wang Liguan,al et,2011.A novel mining model for open-pit mine production scheduling[J].Journal of Central South University(Science and Technology),42(9):2819-2824.
Jia Mingtao,Qinghai Lü,Chen Xin,al et,2017.Application of aggregation staging algorithm in medium and long-term production planning of open pit[J]. Gold Science and Technology,25(4):58-64.
Jiang Chengrong,Peng Ping’an,Wang Liguan,2015.3D visualization production planning in underground mining based on simulating technology[J].China Mining Magazine,24(8):152-156.
Kosztyán Z T,2020.An exact algorithm for the flexible multilevel project scheduling problem[J].Expert Systems With Applications,158:113485.
Li Guoqing,Hou Jie,Hu Nailian,2018.Integrated optimization model for production and equipment dispatching in underground mines[J].Chinese Journal of Engineering,40 (9):1050-1057.
Li Guoqing,Li Bao,Hu Nailian,al et,2017.Optimization model of mining operation scheduling for underground metal mines[J].Chinese Journal of Engineering,39(3):342-348.
Li Junting,Wang Xiaorui,Yang Yuntao,2010.A study on critical chain project network scheduling technology under double constraints[J].Industrial Engineering and Management,15(3):71-75.
Li Rui,Hu Nailian,Li Guoqing,al et,2017.Optimization of mining operation plan based on multi-objective 0-1 programming[J].Metal Mine,46(2):102-108.
Liu Dingyi,Wang Liguan,Chen Xin,al et,2018.Study on multi objective optimization and application of medium and long term plan for underground mine[J].Gold Science and Technology,26(2):228-233.
Liu Xiaoming,Xu Zhiqiang,Chen Xin,al et,2017.Production scheduling in underground mining using mixed interger programming[J].Journal of Southeastern University(Natural Science),38(6):880-885.
Ma Long,Lu Caiwu,Gu Qinghua,2018.Mining production scheduling model and optimization algorithm for multi-metal mine industry[J].Industrial Engineering and Management,23(3):50-58.
Mokhtarian Asl M,Sattarvand J,2018.Integration of commodity price uncertainty in long-term open pit mine production planning by using an imperialist competitive algorithm[J].Journal of the Southern African Institute of Mining and Metallurgy,118(2):165-172.
Ren Zhuli,Wang Liguan,Chen Xin,al et,2017.Optimization of drawing scheduling based on mixed integer programming in block cave mining[J].Chinese Journal of Engineering,39(1):23-30.
Seyed-Omid G,Javad S,2016.Integrating geological uncertainty in long-term open pit mine production planning by ant colony optimization[J].Computers and Geosciences,87:31-40.
Ye Haiwang,Ouyang Jian,Li Ning,al et,2018.Multi-objective genetic particle swarm optimization algorithm for the short-term production planning in a mine[J].Metal Mine,47(11):25-30.
Zhang Lin,2013.Application of key line method in the preparation of coal mining plan[J].Coal Science & Technology Magazine,(3):63-64.
Zhao Aili,2013.Research on Production Schedule of Underground Mine Based on Key Chain[D].Qingdao:Qingdao Technological University.
Zoran M,Suzana M,Vesna M,al et,2019. Long-term room and pillar mine production planning based on fuzzy 0-1 linear programing and multicriteria clustering algorithm with uncertainty[J].Mathematical Problems in Engineering,66(2):13-27.
杜文文,杨扬,2020.基于改进Dijkstra算法的进路搜索研究[J].铁路计算机应用,29(9):62-67.
顾清华,吕艳红,卢才武,等,2020a.多金属露天矿多目标生产计划优化问题建模及求解算法[J].金属矿山,49(4):147-153.
顾清华,马龙,卢才武,等,2020b.露天矿山企业长期生产计划模型与优化算法[J].工业工程与管理,25(1):38-52.
顾晓薇,胥孝川,王青,等,2014.金属露天矿生产计划优化算法的改进[J].东北大学学报(自然科学版),35(10):1492-1496.
侯杰,胡乃联,李国清,等,2016.多金属地下矿山生产计划动态优化[J].工程科学学报,38(4):453-460.
黄俊歆,郭小先,王李管,等,2011.一种新的用于编制露天矿生产计划开采模型[J].中南大学学报(自然科学版),42(9):2819-2824.
贾明涛,吕青海,陈鑫,等,2017.聚合分期算法在露天矿中长期生产计划编制中的应用[J].黄金科学技术,25(4):58-64.
蒋成荣,彭平安,王李管,2015.基于模拟开采技术的地下矿山三维可视化生产计划编制[J].中国矿业,24(8):152-156.
李国清,侯杰,胡乃联,2018.地下矿山生产接续与设备调度集成优化模型[J].工程科学学报,40(9):1050-1057.
李国清,李宝,胡乃联,等,2017.地下金属矿山采掘作业计划优化模型[J].工程科学学报,39(3):342-348.
李俊亭,王润孝,杨云涛,2010.双约束下关键链项目网络计划技术研究[J].工业工程与管理,15(3):71-75.
李瑞,胡乃联,李国清,等,2017.基于多目标0-1规划的采掘作业计划优化[J].金属矿山,46(2):102-108.
刘定一,王李管,陈鑫,等,2018.地下矿中长期计划多目标优化及应用研究[J].黄金科学技术,26(2):228-233.
刘晓明,徐志强,陈鑫,等,2017.基于混合整数规划法的地下矿采掘计划编制[J].东北大学学报(自然科学版),38(6):880-885.
马龙,卢才武,顾清华,2018.多金属矿山工业采掘生产计划模型与优化算法[J].工业工程与管理,23(3):50-58.
任助理,王李管,陈鑫,2017.基于混合整数规划法的自然崩落法放矿计划优化[J].工程科学学报,39(1):23-30.
叶海旺,欧阳枧,李宁,等,2018.矿山短期生产计划优化的多目标遗传粒子群算法[J].金属矿山,47(11):25-30.
张林,2013.关键线路法在煤矿采掘计划编制中的应用[J].煤炭科技,(3):63-64.
赵爱丽,2013.基于关键链的地下矿山生产进度计划研究[D].青岛:青岛理工大学.
[1] 刘鑫, 王李管, 彭朝晖, 邹昀, 鲁芳. 地下矿卡智能调度与生产管理系统设计及应用[J]. 黄金科学技术, 2023, 31(4): 680-688.
[2] 孙越,邹昀,康文宝,王黎明,贾智. 地下无人矿卡智能调度系统框架及应用研究[J]. 黄金科学技术, 2023, 31(1): 133-143.
[3] 李杰林,杨承业,彭朝智,周科平,刘锐凯. 三维激光扫描技术在地下巷道岩体结构面识别的应用[J]. 黄金科学技术, 2021, 29(2): 236-244.
[4] 毕林,王黎明,段长铭. 矿井环境高精定位技术研究现状与发展[J]. 黄金科学技术, 2021, 29(1): 3-13.
[5] 王京华,王李管,毕林. 基于计算机视觉技术的矿井电机车无人驾驶障碍物检测技术[J]. 黄金科学技术, 2021, 29(1): 136-146.
[6] 戚伟,李威,李振阳,赵国彦. 基于CRITIC-CW法的地下矿岩体质量评价[J]. 黄金科学技术, 2020, 28(2): 264-270.
[7] 毕林,段长铭,任助理. 基于RANSAC的地下矿山巷道边线检测算法[J]. 黄金科学技术, 2020, 28(1): 105-111.
[8] 胡建华,徐朔寒,徐泽林,韩磊. 城市地下矿山采矿方法的数值与熵权耦合优选[J]. 黄金科学技术, 2019, 27(4): 513-521.
[9] 贾明涛, 涂小腾, 任助理, 陈鑫, 宋华强. 基于改进最大流最小割算法的露天境界优化及应用[J]. 黄金科学技术, 2018, 26(3): 318-324.
[10] 刘定一, 王李管, 陈鑫, 钟德云, 徐志强. 地下矿中长期计划多目标优化及应用研究[J]. 黄金科学技术, 2018, 26(2): 228-233.
[11] 聂兴信,张国丹. 基于熵值法—突变理论的地下矿山紧急避险系统可靠性研究[J]. 黄金科学技术, 2016, 24(6): 72-77.