基于关键链的地下矿采掘计划编制优化方法
|
谭正华,文阳,王李管,李国泰
|
Optimization Method for Preparation of Underground Mining Plan Based on Critical Chain
|
Zhenghua TAN,Yang WEN,Liguan WANG,Guotai LI
|
|
表1 三贵口矿山530中段采掘计划衔接表
|
Table 1 Connection table for mining plan in 530 middle section of Sanguikou mine
|
|
行号 | 采场序号 | 采场编号 | 工序序号 | 开始时间 | 结束时间 | 所需资源 | 后继采场序号 |
---|
0 | 57 | 530-5203(9-3,9)KC | 1 | 2020/4/8 | 2020/4/14 | 3 | 58、59 | 2 | 2020/4/15 | 2020/4/18 | 3 | 1 | 58 | 530-5202(9-3,9)KC | 1 | 2020/4/15 | 2020/4/21 | 3 | 60 | 2 | 2020/4/22 | 2020/4/27 | 2 | 2 | 59 | 530-5204(9-3,9)KC | 1 | 2020/4/15 | 2020/4/21 | 2 | Null | 2 | 2020/4/22 | 2020/4/27 | 2 | 3 | 60 | 530-5201(9-3,9)KC | 1 | 2020/4/22 | 2020/4/28 | 4 | 61 | 2 | 2020/4/29 | 2020/5/2 | 3 | 4 | 61 | 530-5204(9)KC | 1 | 2020/4/22 | 2020/4/27 | 3 | 62 | 2 | 2020/4/28 | 2020/5/3 | 2 | 5 | 62 | 530-5206(9)KC | 1 | 2020/4/28 | 2020/5/3 | 2 | 65 | 2 | 2020/5/4 | 2020/5/7 | 2 | 6 | 63 | 530-5207(9)KC | 1 | 2020/4/8 | 2020/4/13 | 1 | 64 | 2 | 2020/4/14 | 2020/4/19 | 3 | 7 | 64 | 530-5208(9)KC | 1 | 2020/4/14 | 2020/4/19 | 2 | 65 | 2 | 2020/4/20 | 2020/4/25 | 2 | 8 | 65 | 530-5209(9)KC | 1 | 2020/5/4 | 2020/5/9 | 2 | 66 | 2 | 2020/5/10 | 2020/5/20 | 3 | 9 | 66 | 530-5210(9)KC | 1 | 2020/5/10 | 2020/5/15 | 4 | 67 | 2 | 2020/5/16 | 2020/5/22 | 4 | 10 | 67 | 530-5802(9-3,9)KC | 1 | 2020/5/16 | 2020/5/20 | 4 | Null | 2 | 2020/5/21 | 2020/5/29 | 2 | 11 | 68 | 530-5803(9-3,9)KC | 1 | 2020/4/8 | 2020/4/19 | 2 | 69 | 2 | 2020/4/20 | 2020/4/26 | 2 | 12 | 69 | 530-5803(9-3,9)KC | 1 | 2020/4/20 | 2020/5/3 | 2 | 70、71 | 2 | 2020/5/4 | 2020/5/9 | 4 | 13 | 70 | 530-5804(9-3,9)KC | 1 | 2020/5/4 | 2020/5/12 | 2 | 72 | 2 | 2020/5/13 | 2020/5/22 | 2 | 14 | 71 | 530-5805(9-3,9)KC | 1 | 2020/5/4 | 2020/5/11 | 3 | Null | 2 | 2020/5/12 | 2020/5/17 | 3 | 15 | 72 | 530-6001(9)KC | 1 | 2020/5/23 | 2020/5/27 | 3 | 73 | 2 | 2020/5/28 | 2020/6/3 | 2 | 16 | 73 | 530-6002(9)KC | 1 | 2020/5/29 | 2020/6/5 | 2 | Null | 2 | 2020/6/6 | 2020/6/10 | 1 |
|
|
|