超大断面扁平结构隧道施工参数优化研究
刘宽,莫冠旺,李响,沈平欢,万波,刘建坤

Optimization of the Construction Parameters of Super-large Section Flat Structure Tunnel
Kuan LIU,Guanwang MO,Xiang LI,Pinghuan SHEN,Bo WAN,Jiankun LIU
表4 不同观测断面观测点1的竖向位移值
Table 4 Vertical displacement value of monitoring point 1 at different monitoring sections(mm)
桩号30 m台阶长度40 m台阶长度50 m台阶长度60 m台阶长度
ZK6+790-4.232-4.239-4.246-4.254
ZK6+800-4.274-4.282-4.291-4.301
ZK6+810-4.392-4.399-4.412-4.423
ZK6+820-4.527-4.544-4.552-4.559
ZK6+830-4.637-4.660-4.687-4.683
ZK6+840-4.708-4.724-4.734-4.762
ZK6+850-4.677-4.688-4.691-4.793
YK6+810-3.730-3.745-3.749-3.752
YK6+820-3.766-3.778-3.785-3.790
YK6+830-3.889-3.902-3.908-3.912
YK6+840-4.038-4.051-4.057-4.061
YK6+850-4.167-4.179-4.184-4.186
YK6+860-4.242-4.253-4.257-4.259
YK6+870-4.247-4.256-4.261-4.262